Case studies
AccorHotels Arena at Paris Bercy becomes
a world-class stadium
IN BRIEF
The renovation of Paris-Bercy sports stadium (POPB) was carried out to make it more spacious and modular. The project took an environmentally responsible approach in line with the Municipality of Paris’ climate plan and HQE (High Environmental Quality) standards.
20%
increase in seating capacity.
139
ventilaton fan
Our service
The project:
- to transform this old sports complex into “Bercy Arena 2015”, bringing it into line with other large, multi-purpose stadiums around the world, thus increasing capacity from 17,000 to 20,300 places.
- to make the venue one of the top five arenas worldwide.
Completion of HVAC and fire venting works and restructuring of the chilled water production network to enable -15°C for both ice rinks:
- Adaptation to the site’s complex architecture
- Adaptation to the low environmental impact objectives
- Make use of energy transfers within the site (recycling of heat generated by refrigeration).
- Full purge of the refrigeration system of both ice rinks to replace it with environmentally-friendly chilled water production at -15°C.
- Adaptation to the phasing of the works
Benefits for customers
- Management of a complex, large-scale project with tight deadlines and with a phasing of works that enables events to restart between October and December 2014.
- An environmentally-responsible approach thanks to the installation of highly energy-efficient equipment
- The end result: a sports centre that is more attractive, more comfortable and more environmentally sustainable.
Our latest case studies
Latest news
Find all the topics that make Bouygues Energies & Services news: projects, innovations, public and client events, partnerships, press releases ...
-
-
-
-
-
-
-
-
-
-
-
-
-
- One of the largest photovoltaic power plants in France is being built by our teams.
-
- Sustainability is a unifying theme and major partnerships are being established.
- Our UK team has been selected by VIRTUSfor the turnkey delivery of its LONDON7
- A day of interactive discussion about diversity and inclusion strategy.
- Round table to discuss about national and European support for the hydrogen industry.
- Project Manager Aaron Yule will lead the team in charge of transforming Ashford's lighting.
- Official opening ceremony of the new North Mole thermal power plant
- After 1 year of work, the connected control centre of the OnDijon project was unveiled
- Because preserving health and safety is and will remain the top priority.
- The Top Employers Institute acknowledges the quality of the company’s working conditions and its HR policies.
- Come and meet us to develop innovative energy solutions together
- How is the OnDijon scheme progressing after one year ?
- The results of more than 3 years of work presented at the European Utility Week
- The international event on urban development.
- A successful handover had been completed for Phase 1 of VIRTUS Data Centres’ LONDON5 facility.
- With Sun'R we have combined our skills to support Lamagistère in its energy transition.
- Axione becomes the 86th member of the altnet cooperative.
- Our goal : being innovative together.
- We will demonstrate that it is possible to put technology at the service of well-being!
- SIRO announces investment with joint venture to connect 10 towns to Its gigabit network
- Smart management of public amenities will enable local authorities to improve their performance.
- Mozambique faces electricity supply challenges due to limited infrastructure required to generate and evacuate power.
- Signing of a new contract with Equis, the first regional developer of renewable energies
- Award for centralised technical management system of Marseille’s L2 bypass
- The safety commission met on site and officially recommended that the building could open to the public
- Delivery of 4 solar farms 100km to the north of Bangkok
- New latest-generation production site for a world leader in carbon fibre manufacturing
- An exemplary project combining technical challenges, energy development and local involvement
- Three key aspects of the airport: operations centre, baggage and pass office
- Creation and animation of dynamic trail of light showcasing 39 important sites
- Contract signed with Equis, leading developer of renewable energy in the region
- Five buildings comprising several operating theatres and 250 beds
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45